Federal Procurement
What this guide covers
The dollar thresholds and procurement methods that govern federal buys under the Federal Acquisition Regulation (FAR), plus the systems you’ll use — SAM.gov, GSA Schedules, and the Government Purchase Card. It’s a map, not a contracting course.
Who it’s for
Engineering leads and program staff who need to understand why a purchase has to go a certain way, and what the contracting officer (CO) is working with.
Disclaimer. Not legal or contracting advice. FAR thresholds are adjusted periodically for inflation (FAR 1.109) and by statute. Verify every figure against acquisition.gov (the FAR) before relying on it. Only a warranted Contracting Officer can obligate the government.
Figures below verified 2026-05-29 against the acquisition.gov threshold-changes page and reflect the increases effective October 1, 2025.
⚠️ FAR Overhaul in progress. The Revolutionary FAR Overhaul (RFO) is rewriting and re-organizing the FAR throughout 2025–2026 (interim class deviations began April 15, 2025; rulemaking began October 1, 2025). The dollar thresholds below are current, but FAR part numbers and procedures cited here may move or change as the overhaul proceeds — confirm the part reference against the current FAR or your agency’s deviation guidance.
TL;DR (thresholds effective Oct 1, 2025)
- Micro-purchase (≤ $15,000): buy it directly, usually on the Government Purchase Card. No competition required, but distribute fairly.
- Simplified acquisition (350,000): simplified procedures (FAR Part 13); this range is reserved for small business.
- Above the Simplified Acquisition Threshold (> $350,000): full competition (FAR Parts 14/15) unless an exception applies.
- Buy commercial first (FAR Part 12) and buy off existing vehicles (GSA Schedules) before standing up a new competition.
- You can’t be paid by the government until you’re registered in SAM.gov with a Unique Entity ID (UEI).
Who’s who
- Contracting Officer (CO/KO): the only person with authority to obligate federal funds by signing a contract. Engineers and program managers cannot commit money — only request it.
- Contracting Officer’s Representative (COR): technical eyes on the contract; cannot change scope or money.
- Program / requiring office: writes the requirement and the funding; that’s usually you.
The single most expensive mistake a technical team makes is an unauthorized commitment — telling a vendor “go ahead, we’ll pay you” without a CO. Don’t.
The key dollar thresholds (FAR)
These are the figures that determine how you buy. They were increased effective October 1, 2025 (acquisition.gov/threshold-changes); the previous amounts are shown for reference because older contracts and guidance still cite them.
| Threshold | Current amount (eff. 2025-10-01) | Prior amount | Authority | What it means |
|---|---|---|---|---|
| Micro-Purchase Threshold (MPT) | $15,000 (general) | $10,000 | FAR 2.101 | Buy directly with minimal process; typically on a purchase card. No competition required. (Higher MPTs exist for certain R&D, contingency, and overseas buys.) |
| Simplified Acquisition Threshold (SAT) | $350,000 | $250,000 | FAR 2.101 | Below this, use Simplified Acquisition Procedures (FAR Part 13) — faster, less paperwork. |
| Small-business reserve | 350,000 | 250,000 | FAR 13.003 | Acquisitions in the MPT-to-SAT band are reserved for small business when the CO expects competitive offers. |
| Commercial products/services | n/a | n/a | FAR Part 12 | Buy commercial off-the-shelf with commercial terms before custom development. |
| Truth in Negotiations (TINA) / certified cost or pricing data | $2,500,000 | $2,000,000 | FAR 15.403-4 | Above this, certified cost or pricing data is generally required for sole-source negotiated buys. |
| Cost Accounting Standards (CAS) | $2,500,000 | $2,000,000 | FAR Part 30 | Large contracts trigger CAS coverage. |
Anti-splitting rule: you may not break a single requirement into multiple smaller buys to stay under a threshold (e.g., two 15,000 MPT). FAR 13.003(c). Auditors look for exactly this pattern.
How the value picks the method
≤ $15,000 → Micro-purchase (purchase card), buy directly$15,000 – $350,000 → Simplified Acquisition Procedures, set aside for small business> $350,000 → Full and open competition (sealed bid FAR 14, or negotiated FAR 15) unless: GSA Schedule order, sole-source justification (FAR 6.302), or another exception applies(Thresholds effective 2025-10-01.)
Before standing up any new competition, check whether the buy can ride an existing contract vehicle — that’s almost always faster and is often required.
Systems you’ll actually use
SAM.gov — System for Award Management
The federal registration and search system. A vendor cannot be paid by the government without an active SAM.gov registration and a Unique Entity ID (UEI) (which replaced the DUNS number on April 4, 2022). SAM.gov is also where federal opportunities above the micro-purchase level are publicly posted (it absorbed FedBizOpps/FBO). Registration is free at sam.gov.
GSA Multiple Award Schedule (MAS)
The GSA Schedule (a.k.a. Federal Supply Schedule) is a pre-competed catalog of commercial products and services with negotiated ceiling prices. Ordering off a Schedule (FAR 8.4) is far faster than an open competition because GSA already did the competition. For software and IT, this is usually the path of least resistance. State and local governments can sometimes buy off federal schedules under Cooperative Purchasing (IT, Schedule 70 / the IT category).
Government Purchase Card (GPC)
A government-issued charge card for **micro-purchases (≤ 15,000 MPT increase](https://smartpay.gsa.gov/guidance-and-audits/smart-bulletins/002/).)
Small-business set-asides
Federal policy steers work to small businesses. Above the micro-purchase threshold and below the SAT, acquisitions are reserved for small business when competition is expected. Specific socioeconomic set-aside categories:
- 8(a) — Small Disadvantaged Business program
- HUBZone — Historically Underutilized Business Zones
- SDVOSB — Service-Disabled Veteran-Owned Small Business
- WOSB / EDWOSB — Women-Owned / Economically Disadvantaged Women-Owned Small Business
If your preferred vendor qualifies under one of these, the set-aside path can be both faster and policy-preferred.
Software-specific notes
- Buy commercial first (FAR Part 12). Off-the-shelf and open-source-based commercial offerings are preferred over custom builds.
- FedRAMP. Cloud services handling federal data generally must be FedRAMP authorized at the appropriate impact level. This is a functionality gate, not a price line — an un-authorized SaaS may be unbuyable regardless of cost. See the SSO and data-residency gates in Tools and Software.
- Section 508 accessibility. Federal ICT procurements must meet Section 508 (WCAG 2.0 AA baseline, moving toward 2.1/2.2). Require a VPAT/ACR from the vendor as part of evaluation.
- Open source is allowed. Federal policy (and the DoD/CIO memos on OSS) treat open-source software as commercial software. The cost discussion in Tools and Software applies; the acquisition of support/hosting around it still follows the thresholds above.
Related resources
- Tools and Software — what to buy and the functionality gates (SSO, accessibility, data residency)
- Maryland Procurement — the state-level analog
- Procurement — Overview
- acquisition.gov — the FAR, authoritative
- sam.gov — registration and opportunities
- gsa.gov / GSA Schedules — contract vehicles
Sources (verified 2026-05-29)
| Claim | Source |
|---|---|
| MPT 350,000 / cost-or-pricing-data $2.5M, effective 2025-10-01 | Acquisition.gov — Threshold Changes, October 1, 2025 |
| MPT increased to $15,000 (purchase-card guidance) | GSA SmartPay Smart Bulletin 002 |
| Definitions of MPT and SAT | FAR 2.101 |
| Simplified acquisition procedures; small-business reserve; anti-splitting | FAR Part 13 / FAR 13.003 |
| FAR rewrite / part renumbering in progress | Revolutionary FAR Overhaul |
| Threshold-increase analysis | SmallGovCon — Finalized Increases to Micro-Purchase, Simplified Acquisition, and Other Thresholds |
Thresholds adjust for inflation roughly every five years (FAR 1.109) and FAR part numbers may shift during the overhaul. Re-verify against acquisition.gov before relying on any figure.